G99 vs G98: When Do You Need G99 Instead of G98?

Updated August 2026. G98 and G99are the two main UK connection routes for small solar generation. The dividing line is normally 16 A per phase, which is 3.68 kW on a single-phase home supply. Under that line you usually notify after installation under G98. Over that line you apply first under G99.

3.68kW

Single-phase G98 threshold

16A

Limit per phase

28 days

G98 notification window

Before

G99 approval timing

The 3.68kW threshold in plain English

The practical dividing line is 16 A per phase. On a standard UK single-phase domestic supply, that is usually expressed as 3.68 kW. A generator at or below that size can normally use G98, provided the equipment is type tested and the installation meets the wiring rules. A generator above that size normally falls under G99.

The difference is more than paperwork timing. G98 tells your DNO (your electricity network operator) what has already been connected. G99 asks the network to assess the connection before it is energised. The network may need to check local cables, transformers, voltage rise, export limits, fault levels, and protection settings.

G99 approval comes before connection

Do not install and energise a G99-scale solar system first and apply later. For G99, approval is required before connection. The network may charge an application or assessment fee, and it may set conditions before the system can operate.

G98 vs G99 comparison table

TopicG98G99
Typical sizeUp to 16 A per phase, normally 3.68 kW single-phaseAbove 16 A per phase or more complex generation
ProcessNotification after connectionApplication and approval before connection
TimingSend within 28 days after installationWait weeks or months before installation or energisation
Network decisionNo prior approval for compliant small generationWritten approval or connection offer needed first
FeesUsually no notification feeFees may apply, depending on the network and scheme
Homeowner examples800 W plug-in solar, small type-tested microgenerationLarger rooftop solar, multiple inverters, three-phase systems

Who needs G99?

G99 is common for larger rooftop solar systems, especially 3-6 kW+ domestic arrays where total generation exceeds the single-phase G98 limit. It may also apply when a property has multiple inverters, existing solar plus new solar, export-capable battery storage, or a three-phase supply. Commercial premises usually need a closer G99 assessment because capacity, load, phases, and export arrangements vary more widely.

A system does not become G98 just because one inverter is small. The relevant question is the total generation operating in parallel with the public network at the premises. If in doubt, use the DNO lookup to identify your DNO (your electricity network operator) and ask for the correct connection route before equipment is energised.

When plug-in solar will never need G99

A compliant plug-in solar kit is capped at 800 VAunder the plug-in solar route. That is far below 3.68 kW, so a homeowner using a single approved plug-in kit as supplied should not need G99. The normal route is a G98 notification within 28 days after the kit is connected.

The key condition is that the kit is used as the manufacturer intended. Do not combine kits, modify leads, add extra inverters, or connect extra panels beyond the approved design. Those changes can move the installation outside the plug-in product route and into ordinary electrical design and network connection rules. For wider context, read the plug-in solar UK guide and the guide to whether plug-in solar is legal.


What happens if you exceed G98 limits without G99 approval?

Connecting a G99-scale system without approval can breach the Electricity Safety, Quality and Continuity Regulations (ESQCR) and the network connection rules. Your DNO (your electricity network operator) can require changes, refuse export, or disconnect unsafe or unauthorised generation.

Approval protects the local network

G99 exists because larger generators can affect voltage, protection, and export capacity on a local low-voltage network. The application lets the network check those issues before the system is connected.

What to do next