G98 notification form
Generate a structured ENA Engineering Recommendation G98 Form B notification for a completed micro-generation installation. Download the PDF and email it to your DNO within 28 days of commissioning.
How to submit
Once you have downloaded the G98 PDF, send it to your Distribution Network Operator (DNO). G98 notifications do not require pre-approval — you only need to notify the DNO within 28 days of commissioning a micro-generation system up to 16A per phase.
UK Power Networks — contact details
- Phone
- 0800 029 4285
- Website
- www.ukpowernetworks.co.uk
- G98 form page
- Open DNO G98 page
Submission checklist
- Attach the downloaded
g98-notification.pdf. - Include your contact details in the email body.
- State the installation address and commissioning date.
- Send within 28 days of commissioning.
- Keep the DNO confirmation reply for your records.